Hi!

I have an Event Frame, triggered by an Analysis Expression, which indicates the operation of an equipment. The implemented equation identifies the start and the end time of the equipment operation. This EF Template have an attribute called "Operation Current - Average".

But I have a problem to calculate this attribute: this current needs to be calculated after 2 seconds of the start time of the Event Frame until the end time. This need to be done to eliminate the transient of the signal.

 

I was unable to implement this using PI Formula and the Time Weighted and other functions!

 

It is possible to implement this using Analysis + PI Formula (Attribute) and not using PI EF Gen and Child Event Frames?