AnsweredAssumed Answered

AF Recalculate Event Frame Generation programattically

Question asked by biker2000on on May 10, 2018
Latest reply on May 22, 2018 by biker2000on

I have been working on generating event frames to track batch information for us. I am also using the event frame generator to pull the quality data and compare it with real-time data for each batch. However, since the batch is triggered in real-time and quality data is going to come in 4-12 hours later, I need to recalculate the event frame to pick up the new data.

 

This setup has worked great for generating all of the historical data up until now, but will not work in real-time.

 

Is there a way to force this to happen? 

 

Or can I calculate the batch data based on event frame start and end times outside of the event frame generator?

 

The GUI does not allow you to auto-recalculate event frame generation, so I think it will have to be programmed an then scheduled 2-3 times per day.

 

Thanks,

Justin