AnsweredAssumed Answered

How can I show last 30 days dates in ProcessBook?

Question asked by Kiran324 on Sep 25, 2018
Latest reply on Oct 21, 2018 by Kiran324

Hi All,

 

I am trying to create a graph in PI processBook and I have majorly used the ERD and AF2 features, where my calculation are configured in AF and being pulled into ProcessBooks.

But on the x-axis I intend to show the last 30 days dates. For eg - Today is 25th September, so my axis should show - 24th Sep, 23rd Sep, 22nd Sep and so on.

 

On using BOD functionality in AF analysis, I get the date in "mm/dd/yyyy 12:00:00 AM". I dont require the time here and moreover I prefer dd-mmm format the most.

Is there any way to configure my requirement?

 

All advice are appreciated

 

Thank you,

Kiran Rao

Outcomes