AnsweredAssumed Answered

Configuring Analytics with PI AF

Question asked by DURGAMALLESWARARAO on Sep 12, 2019
Latest reply on Sep 26, 2019 by DURGAMALLESWARARAO

Sebastien Raposo  

 

Hi,

 

1) In this project, how can we take calculation for 50% of OEE metric (OEEScore)? Kindlly assist me

 

   Part 3: The plant supervisor would like to be notified any time a line drops below 50% on the OEE metric. You can use your personal email to demonstrate the capabilities to send notifications to the line supervisors. The supervisors will certainly want to know what each part of the OEE calculation reported during this process excursion.

 

 

2) I'm getting below error when trying to test the notification. 

 

 

 

Thanks,

Mallesh

Outcomes