SQC related questions....  I have a flow of N2 which is showing a lot of signals, outside 3 sigma. This is due to the start-up of the process. 

 

Question: is it possible to "filter"  the first 10 seconds of each startup cycle, before showing the actual values in SQL plot. ? 

 

I managed this so far, but it is not working as I hoped

706320_ST = 11 is the status for start of new cycle

70701D_Volume = 200 is product indication