mathiak

AF Analysis challenge

Discussion created by mathiak on Feb 25, 2020
Latest reply on Mar 11, 2020 by sraposo

Hi Experts,

 

I am facing a challenge in AF.

 

I have a Tag X - Which notifies outage Start and End.

I have a Table Y - Which stores "some duration X" - but the limitation is that the table only acquires its value only every 3 days. In others words ... it is three days behind. So it is not real time.

 

I want to grab "some duration X" From the table Y - when Tag X notifies "Outage". 

 

Please note:

I cannot schedule the analysis "event-triggered" or "Periodic", Because the "Table Y" is 3 days behind.

 

For this reason, Every month on the 3rd or 4th I perform a recalculation on the analysis for "the last month". This fixes my issue. But I am sure there are more "Brainy" "intelligent" ways to achieve it.

Is there a way to recalculate automatically my analyses based on schedule ?

Outcomes