AnsweredAssumed Answered

How to Back Fill back dated Data to a newly created PI Point?

Question asked by Muthulingam-EnQuest on Sep 15, 2017
Latest reply on Sep 20, 2017 by Muthulingam-EnQuest

Hi guys, I have a set of back dated Data from Jun 2015 to Current Date.

I want create a set of New PI Points and back fill them with these data.

 

I tried creating a New "Back Dated" Tag/ PI Point, which was unsuccessful...

The PT Created Date is generated by the system right?

I know this is a stupid question, but is there a way to create back dated Tag?

 

If not, can I back fill the back dated Data into a newly created PI Point?

I have back filled data to an Old Tag before, using PI Config, is it similar?

 

Best Regards,

 

Muthulingam Ramiah